Memo: Project Red Streak Development
As part
of the project team for Project Red Streak, we feel it is imperative to keep
management in the loop regarding our considerations. We have constructed the
initial development plan given the high level criteria. With a start date of
1/1, the project is projected to take 271 calendar days. Our current expected
finish date is the end of September (approximately 9/29). The time differences
are given holidays, weekends, and workflow estimations. Though the project will
start 1/1, it will not actually start till the following day due to the holiday
schedule. Additionally, there is a total of 272 work day items, but the reduced
schedule is due to the overlap of work. We expect that due to the nature of the workflow we will be able to complete all work in this time frame.
As part of this note, please find
two attached supplementary files for illustration. The first is a GANTT Chart
and the other a Network Diagram. I will also provide them in screen shot format
for easier viewing below the note. For those who may be unfamiliar with GANTT
Charts and Network Diagrams please refer to the following items that outline
definitions as advantages and disadvantages of each by
ProjectManagementGuru.com:
“The Gantt, or Bar, chart is the most common schedule format
used on projects. This format is excellent for tracking progress or activity
for tasks once they have been scheduled. In the Gantt chart, every task is
represented by a bar of a time line chart. The left edge of the bar is located
at the time the task is planned to start and the right edge of the bar is
located at the time the task is planned to end. As the project unfolds, the
edges of the bars are often modified to reflect when the task actually started
or ended. This format creates focus for tracking progress because it is clear
to see whether a task should be completed, underway, or pending at any given
time. The Gantt chart is used for daily/weekly tracking of project progress. It
is easy to use and maintain. It has become the most commonly used project
schedule chart because of its simplicity and the focus it creates when tracking
the project. If the task estimates are relatively accurate, this is the
preferred format. However, when task duration estimates are not accurate -
either due to uncertainty in the amount of work or uncertainty in the resource
availability - the Gantt Chart will be a frustrating and counterproductive
scheduling tool. In those cases I recommend the use of the Network Diagram.
The Network Diagram is essentially a flowchart of the project
tasks. This format is a foundational technique for several analytical
techniques. The network is created by determining predecessor and successor
relationships and connecting the tasks based upon those relationships. This
technique will create focus on the handoffs. In a complex project with many
organizations/individuals involved, this technique can provide guidance as to
who is the internal customer for each task. The technique is often viewed as a
foundational technique since most of the advanced analytical scheduling tools
start with the Network Diagram. When task durations are uncertain, the Network
Diagram is often a better technique to use than the Gantt (bar) chart. The
Network Diagram shifts the focus for uncertain tasks from arbitrary start and
end dates to completion of the work and a handoff to the next task/activity.”
Utilizing the GANTT Chart and the Network Diagram we can
easier see some significant items including the critical path and work flow. Our
critical path is through items 2,3,5,8,9,10,11,13, and 14. Please see the Network
Diagram items in pink for a complete reference. We will find the bulk of our
float in the middle of the project. An example of which is with Detailed
Marketing Plans (item 6) and Manufacturing Process (item 7). Items 8 and 8 will
take 50 days and 10 days, respectively, to complete before the next task. While
the depth of the project requires our critical path to be highly maintained we
can find opportunities if delays exist early on.
Please note that a follow up will be distributed shortly regarding
MS Project and business impact.
Regards,
AJ Varghese
Supplementary Material:
GANTT Chart and Network Diagram Definition Source:
http://www.projectmanagementguru.com/scheduleplan.html
Select PMI Definitions:
Schedule network analysis, as defined
by the Project Management Body of
Knowledge (PMBOK), is a technique
used by project managers to analyze schedule information and generate realistic
and optimal project schedules. This
analysis should be performed upon completion of the draft schedule and network
diagram and after each schedule update. Schedule
network analysis involves:
·
Identifying the schedule impact of task
dependencies
·
Identifying critical path tasks and
understanding the impact of the critical path on the schedule. Software tools such as Microsoft Project
automatically display critical path tasks once project information such as tasks,
dependencies, and durations are identified in the tools.
·
Analyzing the effects of schedule constraints
and externally imposed dates
·
Understanding which tasks can experience delays
without delaying the overall schedule
·
Conducting “what if” analysis of various
activity durations (for example, what if the testing activities take twice as
long as is currently planned?)
·
Assessing resource allocation and leveling to prevent resource over-allocation
·
Assessing fast tracking or crashing options to
ensure optimal schedule performance
Analytical Techniques:
PMBOK describes
the following techniques to perform schedule network analysis. For more detail regarding analytical
techniques, which provide valuable information necessary for effective schedule
definition, see PMBOK, fourth edition,
Section 6.5.2. Most scheduling tools
include features that allow utilization of these techniques with minimal
effort.
·
Critical
Path Method – The critical path method
calculates the longest path of planned activities to the end of the project –
the “critical path” – and the earliest and latest date that each activity can
start and finish without extending the project.
Any activity delay on the critical path impacts the planned project
completion date. A network diagram
visually conveys the critical path. This
visibility into the critical path allows project managers to prioritize
activities and take appropriate corrective actions to meet schedule deadlines.
An understanding of the
critical path also allows project managers visibility as to which schedule
activities are flexible – that is, those activities that are not on the
critical path. By looking at a network diagram,
project managers can determine when they have float or slack, which is the
amount of time that any given schedule activity can be delayed without causing
a delay to the start date of subsequent activities (free float) or to the
project completion date (total float).
Knowing when a project has float allows a Project Manager to understand
what tasks may slip and by how much before they have an impact on the project
schedule.
Project Redstreak Criteria:
GANTT Example (for easier viewing):
Network Diagram Examples (for easier viewing split into 3):
No comments:
Post a Comment